Week 0 |
|
Lot staked out. |
Week 1
|
|
Basement excavated. |
Week 2
|
|
Footings set up and poured. Foundation forms set up. |
Week 3
|
|
Foundation poured and waterproofed. Basement plumbing, radon mitigation, gravel laid down. |
Week 4
|
|
Basement slab and garage slab poured. Lumber delivered. |
Week 5
|
|
Walls and floor in basement and main level framed. |
Week 6
|
|
Second story floor and most of walls framed. Garage mostly framed. Windows delivered. |
Week 7
|
|
Driveway and porch cap poured. Second story walls framed. Trusses placed and sheeted.
Stairs built. |
Week 8
|
|
Stairs finished. Second story inside walls framed. Gable roof and bay roofs built. More
framed on garage. |
Week 9
|
|
Main level inside walls framed. HVAC/Furnace installed. Windows installed. Porch footings
poured. Plumbing started. Septic tank/leech fields done. |
Week 10
|
|
Porch columns, beams, and roof built. Rough plumbing finished. Window wells installed.
Backfilled. |
Week 11
|
|
Garage finished. Inside drops/arches/blocking done. Fireplace installed. Pressure tank
installed. Rough electrical done. Roof mostly dried in. Some exterior doors installed. |
Week 12
|
|
Framing finished. 4-way inspection passed. House cleaned up. Porch repoured. Stucco
scaffolding set up. More exterior doors installed. Insulation installed. |
Week 13
|
|
Some stucco underlayment put up. Shingles delivered and some installed. Drywall delivered.
Basement windows installed. |
Week 14
|
|
More insulation installed. More roof shingled. More stucco underlayment done. More exterior
doors installed. Power line run, sanded, and backfilled. |
Week 15
|
|
Power transformer and line hooked up. Drywall hung. More roof shingled. More stucco
underlayment done. |
Week 16
|
|
Gas line run and hooked up. Stucco base coat started inside tarp tent. Drywall taping and
mudding started. |
Week 17
|
|
Drywall taping, mudding, and texturing finished in house. Door to garage replaced. |
Week 18
|
|
Some interior doors installed. More stucco base coat done. Permanent power hooked up. Closet
organizers started. Garage door installed. |
Week 19
|
|
Closet organizers finished. Stair treads and skirts finished. Stucco base coat and color
coat finished. All interior doors hung.
|
Week 20
|
|
New baby arrived. Tarps removed. Garage stairs built. Baseboard and door trim finished.
Paint prep done. Paint started. Cabinets delivered.
|
Week 21
|
|
Prime coat sprayed. Trim and ceilings sprayed. Walls painted. More roof shingled. Sump
pump installed.
|
Week 22
|
|
Paint cleaned up. Loan locked. Some cabinets installed. Railing started. More rock scratch
coat put on. Finish wiring started.
|
Week 23
|
|
Railing finished. More cabinets installed. Phone line installed. More roof shingled. More
wiring done.
|
Week 24
|
|
Roof finished. Soffits started. Tile backer installed. Tile started. Tub/shower tile started.
More scratch coat done. More cabinets installed.
|
Week 25
|
|
Tile finished. Scratch coat finished. Soffits finished. More tub/shower tile finished.
Chimney cut off. Railing stained.
|
Week 26
|
|
Tub/shower tile finished. Railing stained. Countertops finished. Vinyl floors layed.
Fireplace tile finished. Sinks/toilets installed. Appliances installed. Doors
stained. More finish electrical done. Carpet layed.
|
Week 27
|
|
Gas appliances hooked up. Heat registers installed. Cabinets finished.
Railings finished. Mirrors/Shower doors installed. Finish electrical mostly complete.
Final inspection nearly passed. Sinks installed. Wood doors installed. Loan closed.
|
Week 28
|
|
Final electrical done. Temporary Occupancy passed. Moved in.
|
After Moving In
|
|
Garbage cleaned/burned. Garage taped. Driveway made. Sidewalk/porch/walkout poured.
Drop box fixed. Trees planted. Paint touched up. Timber stained. Rock started.
|